Showing posts with label North Queensland. Show all posts
Showing posts with label North Queensland. Show all posts

30 April, 2019

Climate change damage to Queensland's world heritage rainforest 'as bad as Great Barrier Reef’

The wet tropics world heritage area in north Queensland has been damaged by climate change in a manner “equivalent” to coral bleaching on the Great Barrier Reef, the area’s management authority has said.
 Mount Alexandra lookout with a view of the Daintree River
mouth in north Queensland. Local authorities say the area’s
tropical rainforest is in ‘accelerating decline’ due to climate change.
In an extraordinary statement issued on Monday, the authority’s board said the tropical rainforest was in “accelerating decline” and that some of the area’s unique species were at imminent risk of extinction.

Last summer was the hottest on record.

“Extreme heat is the wet tropics world heritage area’s coral-bleaching event equivalent, with some mountain-adapted species, like the lemuroid ringtail possum, unable to survive even a day of temperatures above 29C,” the statement said.


20 February, 2019

Townsville homes may become 'uninsurable' due to flooding from climate change

Houses in flood-hit Townsville and other parts of north Queensland are “on track to become uninsurable”, according to analysis that shows the risk to homes from flooding will more than double under climate change.
 Homeowners in north Queensland will find difficulty
getting insurance as flood risk rises with climate change. 
The modelling, based on current global emissions trajectories, says flooding in Townsville is already about 20% more to likely to occur than previously thought. The total flood risk in the region is likely to increase by 130% by the end of the century.

Climate Valuation, which advises the property and finance industry, said the result would be that more homes would find flood cover difficult to obtain and too expensive.

Home and business owners have reported being caught out by the scale of this month’s flooding in Townsville. Many say they did not have specific flood cover, and that the city planning codes rated properties outside the “one in 100 years” flood zone as effectively flood-free.


Read the story from The Guardian by Ben Smee - “Townsville homes may become 'uninsurable' due to flooding from climate change.”

04 August, 2018

Drought-hit Queensland community welcomes ground-breaking renewable energy park

An Australian-first hybrid wind, solar and battery storage facility is under construction in north Queensland, part of a regional boom in renewable energy.
The 67-metre-long blades will form part of Australia's
largest wind turbines when installed.
The 64-megawatt Kennedy Energy Park near Hughenden, 290 kilometres south-west of Townsville, will combine 12 wind turbines, 55,000 solar panels and 4 megawatt-hours of battery storage, to pump an average of 50MW into the power grid at any time.

Developer Windlab's construction manager Martin Vries said the complementary sources of power generation provided a blueprint for the future of electricity in the region.


18 April, 2018

Dear Mr Adani 'invest in solar not coal'



Read this letter to "Mr Adani" - 

We are leaders from many faith traditions and communities across Australia. We are writing to you to ask you to abandon your proposed mine and instead use the same money to invest in solar energy in North Queensland.

24 March, 2018

Cyclone Nora now expected to cross Queensland coast on Sunday as category three

Authorities now believe Severe Tropical Cyclone Nora will cross the far north Queensland coast some time shortly after midday (AEST) on Sunday afternoon as a category three system.
On Saturday afternoon, Tropical Cyclone Nora was moving south east at 20kph.
At an emergency briefing in Brisbane on Saturday afternoon, Bureau of Meteorology state manager Bruce Gunn said it was expected to cross the coast somewhere between Pompuraaw and the Gilbert River mouth.

"The good news, if I can make any good news out of this story, is that we're no longer expecting a category four system to affect the Gulf but it's still a very severe category three system with very destructive winds at its core," Mr Gunn said.


19 February, 2018

Australia’s first large solar + storage plant connected to the grid

The first large-scale solar and big battery storage installation in Australia – the Lakeland project near Cooktown in far north Queensland – has been officially connected to the grid.
Australia's first large-scale solar/battery installation near
Cooktown in northern Queesnald officially connected to the grid.
The 10.8MW solar facility, combined with a 1.4MW/5.3MWh battery storage facility is located near the very edge of the grid and when first announced in 2016 was being pitched as a world-first for remote, edge of grid technology, and one that would trigger a host of similar projects across Australia.

The project had been due for completion nearly six months ago under its original timetable, but the complexity of the first-of-its-type project – for the developers, the local grid owner, and the market operator – pushed the timetable back.

It has been feeding into the grid since late November, but only recently completed its full sign off with Ergon, the local network operator, and the Australian Energy Market Operator.


Read the RenewEconomy story by Giles Parkinson - “Australia’s first large solar  + storage plant connected to the grid.” 

02 October, 2017

Adani Carmichael coal mine: Former Indian sounds alarm on Adani's track record, mega-mine's viability

India's former environment minister Jairam Ramesh is "absolutely appalled" by the Australian Government's approval of the Adani Group's massive coal mine in North Queensland, which he says will threaten the survival of the Great Barrier Reef, "a common heritage of mankind".
Jairam Ramesh urges the Australian Government
to do thorough financial due diligence on Adani.
Mr Ramesh, an elder statesman of India's opposition Congress Party, also said the Federal Government and Queensland Government have failed to do adequate due diligence on Adani Group's environmental and financial conduct in India before granting environmental approvals and mining licenses.

"Adani Group's track record on environmental management within the country [India] leaves a lot to be desired," Mr Ramesh told Four Corners.


20 May, 2017

Seaweed-fed cows could solve livestock industry's methane problems

Cattle on a CSIRO research station are being fed a mix of grain and seaweed to see if eating algae drastically reduces methane emissions in cows.
A CSIRO trial is underway to if feeding seaweed to
 cows drastically reduces their methane emissions
If successful, the trial could pave the way for a commercial Australian seaweed farming industry to help the overall livestock industry cut its methane emissions.

Agriculture contributes more than 15 per cent to Australia's overall greenhouse gas emissions, and almost 70 per cent of that is from sheep and cattle.

Research last year showed that in a laboratory setting, adding dried seaweed to a cow's diet could reduce the amount of methane it produced by up to 99 per cent.

Those results are now being put to the test in live cattle at the CSIRO's Lansdown Research Station, west of Townsville, in north Queensland.


25 December, 2016

Government guarantees innovative power generator at disused gold mine

An artist's impressive of the first stage
of the Kidston power station of what
will be a 50 megawatt solar farm. 
An innovative north Queensland renewable energy project, which will combine solar and hydro power technology, is a step closer to reality with preliminary construction beginning this week.

The first stage of Genex's power station, a 50-megawatt solar farm built on the site of the disused Kidston gold mine, has been green-lit and was expected to be operational by the end of next year.

The Queensland government signed its first formal Solar 150 program deed of agreement with Genex in Townsville on Thursday.

That agreement set a 20-year price guarantee on the power generated at Kidston, which was able to shore up investors and guarantee construction.

Read Cameron Atfield’s story in the Brisbane Times - “Government guarantees innovative power generator at disused gold mine.”

28 April, 2016

Disused gold mine becomes pumped hydroelectric power plant

A diagrammatic look at what is happening at the
disused Kidston gold mine in north Queensland.
Genex is developing a pumped storage hydroelectric power plant at the disused Kidston Gold Mine in North Queensland.

The plant could potentially generate rapid response, flexible power for delivery into Australia’s National Electricity Market (NEM). The plant would be a highly efficient form of large-scale energy storage that could help manage the introduction of more solar and wind power into the NEM.

An extensive design process has produced an innovative option that could increase the plant’s storage and peaking generation capacity of the project to a maximum of 450 MW over a 5-6 hour period, beating earlier expectations.

The option provides the lowest cost per MW of installed capacity and presents the lowest operating and environmental risk.

Read the ARENA story - “Pumped hydro storage design beats expectations.”